Operation steps for tube furnace charging

Time:2020-11-06 09:22 Click:
     Tubular atmosphere resistance furnace is mainly used in metallurgy, glass, heat treatment, lithium battery positive and negative materials, new energy, abrasive tools and other industries to measure materials under certain atmosphere conditions. The tube furnace sometimes needs access during use. Gas, then how should the operation be regulated to avoid errors during ventilation?

 1. When using hydrogen as a working gas
1. Connect the hydrogen gas circuit and check the leaks with soapy water at each joint to confirm that there is no gas leak.
2. Confirm that each valve is closed.
3. Turn the knob counterclockwise to open the hydrogen cylinder main valve, and turn the knob clockwise to slowly open the outlet pressure reducing valve to make the outlet pressure at 0.1MPa.
4. Turn on the power of the mechanical pump, open the tube furnace outlet valve and the two valves on the mechanical pump gas path, and pump for 5 minutes.
5. Close the two valves on the gas path of the mechanical pump, close the outlet valve of the tube furnace, and turn off the mechanical pump.
6. Open the upper gas path control valve counterclockwise so that the arrow points to the "open" position.
7. Adjust the flowmeter knob counterclockwise to make the reading at 20ml/min.
8. Turn the knob counterclockwise to open the air inlet valve of the tube furnace until the barometer reads zero.
9. Open the inlet valve of the tube furnace and open the red outlet valve on the hydrogen gas path.
10. The tube furnace can only be heated after 10 minutes of hydrogen gas. Before heating, adjust the flowmeter knob counterclockwise to make the bubbles in the Erlenmeyer flask appear at a rate of 2 bubbles per second.

Ⅱ. When using inert gas as working gas
1. Connect the working gas circuit and connect the gas outlet end of the tube furnace to the mechanical pump.
2. Open the inlet valve of the tube furnace, turn on the power supply of the vacuum pump, open the outlet valve (be careful to hold the flange to avoid excessive force on the furnace tube), and evacuate the corundum tube and gas pipeline.
3. When the vacuum gauge of the tube furnace reaches -0.1 (when the pointer reaches the end), close the outlet valve and close the inlet valve.
4. Turn the knob counterclockwise to open the main valve of the gas cylinder, and turn the knob clockwise to slowly open the outlet pressure reducing valve so that the outlet pressure is 0.004MPa (2 cells).
5. Turn the knob counterclockwise to slowly open the tube furnace air inlet valve; pay close attention to the tube furnace air pressure gauge to confirm that the air pressure is below 0.08MPa (if the air pressure is higher than 0.08MPa, open the tube furnace air outlet valve to vent).
6. Tube furnace air pressure gauge When the air pressure is stable, close the tube furnace air inlet valve, open the air outlet valve, evacuate to -0.1, and close the tube furnace air outlet valve.
7. Repeat steps 4 and 5 twice.
8. Turn off the mechanical pump and open the air inlet valve of the tube furnace.

Please leave a message here. We will reply you in 24 hours.

Contact Information

E-mail:
web@kejiafurnace.com
Address:
Room 1505, Building 9, No. 26 Dongqing Street, High-tech Industrial Development Zone, Zhengzhou City, Henan Province
QQ tel Email WhatApp FaceBook

Tel Number

181-3719-5600

Email

web@kejiafurnace.com

WhatsApp

+86/18037178440

FaceBook

Zhengzhou/Kejia

kejialiuyan